Hi,

Can anybody tell me how would I get automatic split on maintenance order operations?

Is there any separate transaction for operation confirmation at the level of splited operations?

Regards,

Accepted Solutions (1)

Accepted Solutions (1)

rakesh_mane
Active Contributor
0 Kudos

hello

The automatic way is not possible in STD SAP .Go for Enhancement or You need to do it manual at Requirement Asignment Tab at Opertion Level.

Regards,

Rakesh

former_member221085
Participant
0 Kudos

Hi,

What about confirmation, is it possible to confirm splited operations?or confirm operation on the level of personal (that are defined in HR assignment of work center and use in operation split of order) hours?

rakesh_mane
Active Contributor
0 Kudos

Hello,

You can do the Cofirmation of Splited Hours on The Basis of Person assign to that Perticular Work in Order Have look Iw42 or Iw44

Regards,

Rakesh

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

Yes, generating of automatic split at the operation level is definitely possible at the time of Order Create.This is available through the partner determination functionality.Have a look at [Sap Help|http://help.sap.com/erp2005_ehp_04/helpdata/EN/42/11112e460d73aee10000000a114b54/frameset.htm] for additional information.

Regards

Narasimhan

Former Member
0 Kudos

Hi Expert,

I don't think you can get automatic split on maintenance order operations. You need to assign operations to objects.

Confirmations should happen in the usual way.