SAP APO SNP planned order

Former Member
0 Kudos

Hi,

I am basically from PP background and just started working in APO SNP. after running SNP optimzer,not able to see the operation details in SNP planned order ( SNP planned order has only receipts, requirements ). could you please help me how to get operation details in SNP planned order.

Thanks

Krishna.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

HI Krishna

You cannot see the operations in th SNP order. You can see the same in the PPDS order.

Rgds, Sandeep

Former Member
0 Kudos

Hi

Thanks for your information.

Thanks

Krishna.

Edited by: Krishna72 on Oct 26, 2010 10:36 AM

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

SNP Planned Order:

1 . SNP Planned Orders wil give details about Order start date and finish date .

2. During SNP Planned Order creation a basic scheduling will happen.

PPDS Planned Order

1. PPDS Planned Orders will give details about when the actual production is start and finish.

2. During PPDS Planned creation the Machine time details defined in the routing routing or recepie will be take into account.

3. Leadtime scheduling will be carried out to calculate the exact production start date and finish date.

Thanks,

nandha

Former Member
0 Kudos

Hi nandakumar,

Thanks for your information.

Thanks

Krishna.

Former Member
0 Kudos

The SNP planned order(right click display details) should tell you which PPM is being used. The PPM itself should have the details. Is that what you're looking for?