Hi All,

We are getting the error "no valid business partner assigned for user" as soon as the change document saved for next status "in development".

Now BP has been assigned for the user and he is able to create the new change request and then change document but the error in the previous change document cannot be nullified even after the BP is created for the user.

Is there any way we can remove the error in the previous change document?

Thanks

Tripti

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Thanks All.. issue is resolved.

Former Member
0 Kudos

Hi Tripti.

If you haven't fixed this error, try using the action "Recheck correction" to re-validate the change document

or if the user field is visible/changeable in the screen (i.e. current processor), try changing it to "blank" and save and then re-rtype the user again.

Regards,

Tess

Former Member
0 Kudos

Hi,

Can you please check the note 861116, 550055

Hope you have assigned the bp in the orginzation in which user is assigned. Hope the same

BP has role Employee and Userid is assigned to that BP.

Regards,

Deepanshu