Skip to Content
avatar image
Former Member

Activity types values are missing in COR6N

Hi Experts.

I am not able to see the planned activity types over COR6N screen, we are in S/4 HANA system.

Even after clicking the tab "Actual Data" , activity values are not getting copied from the order, all activity fields will be blank, hence we are updating all the 6 fields manually.

We checked following settings:

Standard value key with 6 activity types

Cost center, activity types, Formulas defined and assigned in Resource and price planning also done.

OPK1- Default values selected as "immediate proposal" for Quants and Services.

Parameters for Order confirmation: All check boxes activated except "include finally confirmed operations".

Your help is appreciated

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

0 Answers