Hi all,
I am facing a problem as
In MD04,mrp element is showing PldOrd,while user is saying he always looks here Preq.
can anybody suggest that where the setting,by which Pldorder is comming instead of Preq.
Hi,
Please check the control parameter for MRP run.
In MD03 or MD01, select ' Create purch req as 1 ', then it creates purchase requisitions.
Thanks,
Venkat
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi ,
in MDO4 Click on the "Expand Header Material " button just left to the Material Field on the screen.
you will see the additional screen shown. here go to Tab " Overview of Material Data" here you see a Filed " Procurement Type"
If its have a Value = F then only you will see Preq generated for that material/ Plant after Planning run (MRP run).
If it has a value - E then a PLnOrd will been after planning run.
If you have access to MM02 go and change the value in MRP 2 view to F if you need Preq. to appear after planning run.
You should manually delete the Plnord Planned order and then change in MM02 to F and do MRP run to get Preq.
Additionally , you can view the Change log in MM02 itself to fiugre out who changed it.. ( MM02 > MRP2 view> Environment-->Display changes)
Hope this helps.
Thx
MJ
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
85 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.