Oct 22, 2010 at 09:49 AM

Confirmation Transfer Issue through CATA run

53 Views

Hi All,

In CJI3 report, still Actual Cost is appearing against reversed timesheet entry.

Scenario: User had done some timesheet entry against Network activity and ther CATA job run. After some days, User again changed the timesheet with New Network and Activity number. But still CJI3 report is showing cost against old Netowrk Number. Its not getting Cancelled/reversed. In CAT2/CADO/CATS_DA its appearing properly.

I think there may be some issue in CATA job run.

Could you please tell me what are the possible causes that s why these confirmation can not get cancelled?

Also if you provide solution, then it would be great for me.

Many Thanks in advance.

Swapnil Kharul