  • Dec 08, 2016 at 03:56 AM

    I don't believe it's possibe to do what you want. In order to create the inspection lot the system needs to calculate samples and the physical samples required. You can't access results recording (Status REL), until this is done. Since you can't access results recording, you can't manually assign a physical sample number. It might be possible via QA02 but I can't say I've ever attempted this. It wouldn't surprise me if the system would choke if you attempted this as a sample-drawing calculation could require creating several different physical sample numbers including reserve samples, and combinations of independent and pooled samples.

    Exteranl number ranges are really used for manually creating physical sample numbers such as for competitor samples,

    If you really require this, I would put the question directly to SAP as I don't think the current system design can support what you want.

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hi Craig,

      Thanks for details help on this however I will check once again on this and try to put existing functionality as much as possible.

      Thanks for understanding & support.

      satish

  • avatar image
    Former Member
    Feb 20, 2017 at 04:49 AM

    Thank for explanisation.