Skip to Content
avatar image
Former Member

planned delivery time field in sale order

Dear All,

During creation of STO at item level under delivery TAB "planned delivery time" field is showing with edit mode, I want to activate this field for sale order creation / change also. Plz advice how I can do this.

regards,

sps.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • avatar image
    Former Member
    Oct 20, 2010 at 06:04 AM

    Dear SP

    This field is laready there in the MRP-2 of the material master. This is used to calculate the no. of days to procure a material/service externally. Why do you want to activate this in sales order.

    Thanks

    Shuktiz

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Dear Shuktiz,

      I want to change the date of this field for particular sale orders to early schedule the production.

      regards,

      sps.

  • avatar image
    Former Member
    Oct 20, 2010 at 10:58 AM

    This is not possible in standard SAP.

    Thanks

    Shuktiz

    Add comment