on 10-18-2010 3:52 PM
We face the problem that when we enter a confirmation to a purchase order the availability check in VA02 still does not suggest a date in the sales order (same article). The MD04 of the article seems to be correct (LA-AB).
We implemented a new plant.
In the old plant it works allright even with the same material.
Checking group for availability check: 02
Checking rule: A
The only difference between the two plants I see is that there is a new confirmation control key in MM.
It is MRP-relevant and GR-relevant.
Do you please have any ideas what could be the reason for the problem in availability check?
We would expect to get a new schedule line for the item with the date of delivery by the supplier (plus 2 days).
If there are facts that you need to know to answer the question please don't hesitate to tell me.
I will try to give you the information.
Thank you in advance.
Hello,
the MD04 is a purchase view-Pls try to use CO09 which gives you correct result(This is sales view)
Thanks and best regards
L
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
88 | |
10 | |
10 | |
6 | |
5 | |
5 | |
5 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.