Former Member
Oct 18, 2010 at 08:15 AM

Revenue Budget management through Internal Order

106 Views

Hi!

My client is asking for availability control for revenue budget also.

I have created one order type in order to accept revenue postings ( ticked for commitment update also) and assigned budger profile.

The revenue postings are happening to that internal order, but not giving any error messager once, revenue budget is crossed.

The main reason being , the revenue elements are excluded from assigned values for internal order.

Entries in this color make no contribution to the assigned value

W: Value type not relevant (<> Actual/staistical actual/commitment)

S: Settlement to object with no budget control

R: Revenue cost element

C: Cost element is exempt cost element

Order Current budget Assigned

500000 6,000.00 INR 0.00 INR

COSP 2010 04 0043200000 0000000253 COIN H INR 19,800.00- INR R