Skip to Content
author's profile photo Former Member
Former Member

Production order different M/C confirmation

Hi all,

If possible to entry in single work order two machine production confirmations.

Example:

Work order: quantity 1000 pcs

M/C used: High -500 Pcs, Low speed -500 Pcs for this flow how can make it entry in production order information

Advance thanks

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • author's profile photo Former Member
    Former Member
    Posted on Oct 15, 2010 at 09:27 AM

    Mr.Jack

    Yes it is possible to confirm same Production order with different work center.

    you have to do the changes in OPK0

    1) Create profile SAP000

    AREA Selection:-

    2)Header area select order/sequence/operation

    Detail Area:-

    3)quantities :yield/scrap/rework/reason/display

    4)Activities: Activity 1 to 6

    5)Personnel : Include work center & Posting date

    select Remaining you want to display on the screen in co11n

    You can also work center as a mandatory option at confirmation

    Hope this helps you & serve your purpose

    Thanks

    Harish

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.