change from service activity to internal activity

Dear All,

In my current project i got a scenerio where client is changing the plan on activity whether internal or service. It means one week before the execution they may change the nature of activity and do it themself.

Now in current system i am able to change from internal to external by changing the control key.

Also i am able to change external from internal. but once i have made it service and i want to make it internal, system is giving the error " Control key PS01 is not valid for services" . Means i am not able to change service activity into internal.

Kindly suggest how to change from service to internal.

Regards

Abhishek Sinha

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Oct 15, 2010 at 04:18 AM

    Hi,

    in txn opsu for ps01 indicate the service checkbox and see.

    regards,

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Abhishek Sinha

      Hi Abhishek,

      I think you can try to make use of activity element in your scenario. If internal activity exists, and they decide to go for service - service element can be added & vice versa. Activity elements are supplementary in nature, so I guess this might help you.

      Regards

      Shrikant