cancel
Showing results for 
Search instead for 
Did you mean: 

change schedule line date

Former Member
0 Kudos

Dear All,

I have a requirement where required delivery date for one divisions material

in sale order and STO should automatically propose todays date plus 10 days i.e.

if any sale order or STO created today then required delivery date in STO and

SO should show 24.10.2010.

Accordingly we have maintained planned delivery time in material master 10 days in MRP2

view and it is working fine but another requirement is that user can reschedule the

delivery and he can change the schedule line date in So (RV45A-ETDAT) before or after

10 days in VA02 but it is not allowing to change it is considering todays date + 10 days.

In STO it is allowing for change the delivery date (MEPO1320-EEIND).

Plz advice how I can make the field RV45A-ETDAT changeable in sale order through VA02.

Regards,

sps.

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi Mr.Shukla,

pls check whether you have checked the field"fixed date and quantity" in the schedule line data of that particular line item?

Regards,

Ramesh.

Former Member
0 Kudos

Dear Mr Ramesh,

I am not seeing any such field "fixed date and quantity" as mentioned by you in schedule line data for the line item.Can tell me why this field is not coming the sale order?

regards,

sps.

Former Member
0 Kudos

Dear All,

Plz give some solutions for this.

regards,

sps.

Lakshmipathi
Active Contributor
0 Kudos
I am not seeing any such field "fixed date and quantity"

Really I am surprised to note this. If you were creating a sale order from standard order types or copying the standard ones, then you should be in a position to see this field. Check once again by going to sale order schedule line tab where from left you can see the dates. Above this date tab, Delivery time and above that you can see "Fixed date and qty".

thanks

G. Lakshmipathi

Former Member
0 Kudos

Dear Lakshmipathi,

Thanx for the reply, actually I was looking on line item level only.The field is available in schedule line tab above the delivery date same as explain by you But it is not working If I checked this field and want to change first date in line item(if it propose by 04.11.2010 and I want to change it by 28.20.2010) it is replacing by old date (todays date plus 10 date). Can you help me out in this problem.

regards,

sp shukla.

Former Member
0 Kudos

Hello,

If you want a sales order to have the requested delivery date automatically populated with today's date +10 business days, this can be maintained via the following SPRO path:

SAP IMG --> Sales and Distribution --> Sales --> Sales Documents --> Sales Document Header --> Define Sales Document Types

Go into the sales document type you would like to maintain. In the section "Requested delivery date/pricing date/purchase order date", there is a field Lead Time in Days. Put 10 in here, and the requested delivery date will automatically be set to +10 days when an order is being created.

Planned delivery time in the material master is for when you're out of stock and the system proposes the next available delivery date. If you have stock on hand, when the availability check runs the system will use the line level delivery date. At order entry, when a line item created this line level delivery date is taken from the requested delivery date.

I hope this helps you.

Former Member
0 Kudos

Dear Andy,

My requirement is for only some specific materials which are under one division and I can not use seperate document types because this requirement is only for one plant only.Give any other solution for this.

regards,