Independent requiement is not comsumed in strategy group 10

HI Gurus,

My material is maintained as :

Strategy group : 10 Make-to-stock production

Consumption mode 2 backward anf forward

Indenpendent requirement is created as LSF.

in MD04, it shows like below:

stock 5

IndReq LSF 20- 15-

CusOrd xxx 1- 16-

Reqtype of Cusord is KSL.

after i finish PGI, it shows like below:

stock 4

IndReq LSF 20- 16-

So i have two questions:

1:why the indReq is not consumed.

2:how to control when to cosume inreq , when sales order is created or when PGI is done?

BR,

Dragsky

Add a comment
10|10000 characters needed characters exceeded

Related questions

4 Answers

  • Posted on Oct 14, 2010 at 07:15 AM

    Dear

    In Plng Strgy 10 , PIR will not be consumed rather it will be reduced on goods issue to Sales Order .

    Can you pelase Check in OMPO-Maintaining Requyirement Classes for PIR -Requirement Reduction Indicaotor either Blank or X ?? It should be Blank not X

    Regards

    JH

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Oct 14, 2010 at 07:21 AM

    Hi

    In strategy 10 PIR is consumed when delivery is done against sales order.

    This is controlled at the time of definition of MRP strategy IMG->PP->Demand Mgmt->PIR->Planning strategy. by assigning requirement class to the strategy.

    For st 10 requirement class is 100. for consumption following options are available

    No consumption with customer requirements

    Consume planning with assembly

    Consume planning w/o assembly

    Consume planning material (w/o assembly)

    for 100 option 0 is maintained which is standard sap setting not recommended to change. If you need a different behaviour you can create a new rer class and strategy as per your need.

    Regards

    Abhishek

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Oct 14, 2010 at 10:34 AM

    Hi ,

    Thank you for your response!

    I know the sap standard setting is to consume PIR when do PGI, but in my case, no PIR is consumed when i fnish PGI, i wanna know the potential reasons.

    BR,

    Dragsky

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member

      Dear Dragsky,

      First thing in Strategy 10 is PIR gets reduced ( Not consumed )

      PIR will be reduced once Good Issue is done for the delivery/sale order.

      You can see this quantity as withdrawn quantity in the schedule line tab in MD63.

      Hope it clarifies

      Regards

      Madhu

  • author's profile photo Former Member
    Former Member
    Posted on Oct 15, 2010 at 06:40 AM

    Hi ,

    There is no withdrawal quatity in MD63 in my case, do you know why?

    BR,

    dragsky

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.