Change Req. status change to 'Confirmed' when UC status changes to Completd

Dear all,

When I am completing the urgnt correction(SDHF), the status of change request (SDCR) is not getting changed to 'Confirmed'.

Is it a standard behaviour ?

How to configure for automatic status change of Change Request to 'Confirmed' when urgnt correction is completed.

Regards

PK

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    avatar image
    Former Member
    Oct 15, 2010 at 08:24 AM

    Hi,

    Yes. It's a standard behavior.

    If you want to do so, add a processing parameter to the action CLOSE.

    What to be set is like that of PRODUCTIVE action of SDHF_ACTIONS profile.

    ELEMENT: PREDOC_STATUS

    Data type: J_ESTAT

    Initial value: E0006 <- status "Confirmed" of SDCR

    Regards,

    Kazuhisa

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Hi,

      Here is another way to change the status of precede document.

      SPRO: Change Request Management -> Extended Configuration -> Change Transaction -> Change Transaction Types

      Define Status Attributes

      SDHF / SDHFHEAD / E0008 / / Completed / 6 / SDCR / SDCRHEAD / E0006

      This entry means that if the status of SDHF comes to E0008 then the status of SDCR turns into E0006 automatically.

      Regards,

      Kobayashi