Hello,

I am looking for a user exit to round the order quantity when converting the planned order to a process order through COR7, COR8, and MD04. Does anyone know of a user exit that I can use?

Thank you,

Accepted Solutions (0)

Answers (1)

Answers (1)

rammohan_shenoy
Active Contributor
0 Kudos

Mike,

Just wondering if you are fine with having the system to do the rounding at planned order stage itself.

As this can be done by using either a Rounding profile or Rounding value whichever makes more sense.

thanks,

Ram

Former Member
0 Kudos

Hello Ram,

We have looked into both the Rounding profile and Rounding value but they do not fit our business model. I am looking for an alternative to do the rounding.

Thank you,

Mike