How to make Open Sales Orders consider unallocated stocks in MRP run

Dear Experts,

Maerial BOM MATERIAL TYPE STRATEGY GROUP PLANNING STRATEGY

Req-DM Req-CU

3. TF180TK fert 20 KE make-to-order

2. TH300TK halb 20 KE make-to-order

1. TA300TK roh 10 LSF KSL make-to-stock

As listed above material in line no.1 is required to produce 2 and

2 is required to produce 3.

I have open open sales orders for material TF180TK(fert).

What settings do I need to effect, to make the System consider Stocks & Open Purchase Orders for material TA300TK (roh) which are not allocated to these Sales Orders , when MRP run is carried out at plant level using MD01?

Regards

Add a comment
10|10000 characters needed characters exceeded

Related questions

3 Answers

  • Best Answer
    Posted on Oct 12, 2010 at 06:53 PM

    Dear Bisolaania,

    Maintain a Individual/collective requirement as 2 - collective requirement for Material TA300TK in MRP 4 view

    NO need to maintain a planing strategy for HALB and ROH for your requirement.

    Maintain a planning strategy 20 and Maintain a Individual/collective requirement as 1 - Individual requirement for TF180TK, while creating check in Va01/Va02 In procurement tab, the requirement type is KE or not

    Maintain Individual/collective requirement as 1 - Individual requirement for material TH300TK

    Maintain a Individual/collective requirement as 2 - collective requirement for Material TA300TK in MRP 4 view( This setting allow the material to consider stock and PO for the sale order requirement)

    and run the MRP with planning mode- 3 delete and recreate in MD01 and then Check

    Edited by: Sundaresan . E. V on Oct 13, 2010 12:24 AM

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Oct 12, 2010 at 05:20 PM

    Dear Bisolaaina,

    For ROH Go to MRP - 4 view

    For option indi/coll indicator make it as - 2 ( collective requirement )

    when you run system will consider the stocks & Open Purchase Orders

    Regards

    Madhu

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Oct 12, 2010 at 06:38 PM

    bisolaaina,

    the reason the Made to order settings on FERT material is carried over to lower subassembly halb & raw material is that your MRP4 view has Individual/coll = blank or 1 (individual) for your material HALB & ROH.

    Change this setting Individual/coll = 2 (collective). System will then consider individual requirements of FERT material collectively and use existing stocks & purchase orders.

    Once you made changes in material master you will have to recreate sale orders as existing sale orders will not read updated material changes.

    I am sure this will help resolve your issue.

    Thanks,

    Ram

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.