Dear Experts,
Maerial BOM MATERIAL TYPE STRATEGY GROUP PLANNING STRATEGY DESCRIPTION
Req-DM Req-CU
3. TF180TK fert 20 KE make-to-order
2. TH300TK halb 20 KE make-to-order
1. TA300TK roh 10 LSF KSL make-to-stock
As listed above material in line no.1 is required to produce 2 and
2 is required to produce 3.
I have open open sales orders for material TF180TK(fert).
What settings do I need to effect, to make the System consider Stocks & Open Purchase Orders for material TA300TK (roh) which are not allocated to these Sales Orders , when MRP run is carried out at plant level using MD01?
Regards
Add a comment