Today's scheduling

Hi,

There are some demands whose supply is planned in the past as capacity is not available in the future

We do not want CTM to generate supply in the past(we are not maintaining any ORDER START DATE as -ve)

Do we have anything like this-----the system backward schedules and sees that the start date is falling in the past and then does a forward scheduling to plan for the same in the future

Kindly suggest,

SS

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    avatar image
    Former Member
    Oct 12, 2010 at 08:45 AM

    Hi,

    You can maintain a positive entry in the order creation start date.

    Thanks,

    nandha

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Hi,

      Planning horizon defined is 23.09.2010 to 22.09.2011..

      Demand on 23.11.2010

      Order creation start date - 10-

      Running the CTM will create orders 05.10.2010

      Demand on 23.11.2010

      Order creation start date 10

      Running the CTM will create orders on 26.10.2010.

      Though sufficient capacity is avaialble as on today itself , since we have defined order creation to be started from current date +10 days CTM run has created orders on 26.10.2010 though demand exists on 26.11.2010.

      If by any chance the order creation date goes before the planning horizon start date, orders will be created as on date.

      If by any chance the order creation date goes after planning finish date, orders will not be created.

      Hope you are clear.