Availability control

Hi gurus,

We have implemented funds mgt availability control in public sector mgt-former budgeting.

For the above case, multiple GL accounts are assigned to 1 commitment item, hence, the control only available at commitment item level.

Now, we are looking to implement the availability control (fr expense & capex item) at GL acct level instead. Can any expert advise how to do this? Shall we implement Internal order? How is the internal order works?

Regards

Chew Lin

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

1 Answer

  • Posted on Oct 12, 2010 at 07:21 AM

    Hi,

    You are mixing things... Internal order budget control is managed in CO and has nothing to do with your requirement to have control on the level of G/L account. But, you can perfectly achive this in FM. Just rebuild your FM structure, creating instead of one commitment item, the number of entities which correspond to G/L accounts. Define the proper derivation strategy for this and that's all.

    Regards,

    Eli

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.