PO - Question for Release Indicator = 1 (Cannot be changed)

็ำ็Hello.

I have some problems about release stretegy. I don't want to change any values in PO after released so I set release indicator to 1 - cannot be changed.

But I have problem when vendor sent the meterial less than PO quantity I must set completed delivery in PO - Me22N. I cant save the changed PO.

When I change to use other release indicator, User can change the PO value -> My boss don't need this

Is there other solution for this problem??

Thank you.

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • author's profile photo Former Member
    Former Member
    Posted on Oct 12, 2010 at 11:24 AM

    Hi,

    There is no alternative for the current setup and expectation.

    However did you consider using Tolerance on Release Indicatorr instead of "Cannot be changed"

    But it might need some change management exercise.

    Hope this helps.

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.