Dear Expert,
I need your Help regarding to this issue :
I have Product P-200 for location 1000 (Location type 1001) , and Valid PPM with Input Product R-200
This Product R-200 is assembly and have PPM in Different Location 1100 (Location Type1001)
When I run Heuristics in SNP , I can't find Dependent Requirement for this item in this Product Location R-200 - 1100 Based on Demand for Product Location P-200 1000
Could you Please help mr how i can implement this scenario
Kindly Regards
Rami
Hi,
1. The product R-200 in loc 1000 should be defined as ext proc ( Proc type F).
2. The same product should be defined as in house production in loc 1100.
3.A Transportation lane should exist from 1100 to 1000 for this product.
4.Then take Heuristic run.
5. Dep reqmts will generate.
Or refer notes 619898
Thanks,
nandha