Skip to Content

Produce assembly in onther Location

Dear Expert,

I need your Help regarding to this issue :

I have Product P-200 for location 1000 (Location type 1001) , and Valid PPM with Input Product R-200

This Product R-200 is assembly and have PPM in Different Location 1100 (Location Type1001)

When I run Heuristics in SNP , I can't find Dependent Requirement for this item in this Product Location R-200 - 1100 Based on Demand for Product Location P-200 1000

Could you Please help mr how i can implement this scenario

Kindly Regards

Rami

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • author's profile photo Former Member
    Former Member
    Posted on Oct 12, 2010 at 05:04 AM

    Hi,

    1. The product R-200 in loc 1000 should be defined as ext proc ( Proc type F).

    2. The same product should be defined as in house production in loc 1100.

    3.A Transportation lane should exist from 1100 to 1000 for this product.

    4.Then take Heuristic run.

    5. Dep reqmts will generate.

    Or refer notes 619898

    Thanks,

    nandha

    Edited by: S.Nandakumar on Oct 12, 2010 7:06 AM

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Oct 13, 2010 at 11:16 AM

    UN

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.