Hi,

Iam performing auto goods receipt of finished material at the time of production order confirmation, now i have to enter receiving storage location manually under goods receipt tab of production order. is there anyway it should be filled up automatically from material master? i tried entering storage location in MRP 4 but its not working.

Please suggest.

Add a comment
10|10000 characters needed characters exceeded

Related questions

5 Answers

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Oct 12, 2010 at 12:40 PM

    Hi All,

    Thank you for all your responses. in MRP 2 view iam not able to see production storage location option where as i entered those information for all raw material for doing backflush. my finished product is a KMAT material. is that a problem?

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Oct 11, 2010 at 09:10 PM

    dear friend,

    please go to MRP 2 view and set your storage location in the field Prod. stor. location.

    (make sure you have the same setting in Work scheduling tab)

    good luck.

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Oct 12, 2010 at 02:59 AM

    Dear Sprint,

    In MRP - 2 view for option Prod. stor. location mention the required storage location

    Same gets copied in production order and while doing GR

    Regards

    Madhu

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Oct 12, 2010 at 07:53 AM

    Hi,

    You can maintain the storeage location in Material Master MRP 2 view, these will copied to new creation production orders

    If you want to update existing open production orders then goto CO02-->Goods Recipt --> field Storage Location

    Regards,

    Sankaran

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Oct 12, 2010 at 09:25 AM

    Dear

    You need to maintain the following to have Auto Goods Reciept

    1.Correct Operation Control Key -PP03 having Auto GR activated and Final Confirmation in Routing .Check in Define Control Key in SPOR-Shop Fllor-Master Data -OPJ8 .Here Milestone Confriamtion should be marked

    2.Check in MRP2 view wether you have Production Storage Loaction maintained or Work Sxheduling view .If you have Production Version in MRP4 view , please check the same .

    4.

    3.In OPKP-define Production Scheduling Profile -You should chekc in PSF-Goods Receiept -Auto GR check box marked .

    4.You can also enetre manully PSL in CO02-Production Order -GR tab -check the same before confirmation posting

    5.In confirmation posting chekc in Goods Movemenet tab wether PSL is poplating or not .If not eneter the same and carry out .

    Make sure that FG is maintained in Production Storage Loaction in MM01

    Hope this clarifies your doubt

    regards

    JH

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.