Hi,

We have two type of forecasting in SAP APO DP:--

1. rolling forecast -


on monthly base

2. mid month forecast -


on every 15th day of month

For this data is to be populated from SCM - BI cube to PA, for this we use standard program "/sapapo/rtsinput".

What happens that regarding the rolling forcast the data is uploading correctly from SCM -BI Cube to PA,

but in midmonth forecast there is mismatching of the data. e.g. if data of any product is 350 in SCM-BI Cube after uploading in PA , it will be seen in planning book as 290 (mismatch).

I have tried to upload from /sapapo/tscube -


same this is there.

Could any one please let me know what should be done to correct this.

Add a comment
10|10000 characters needed characters exceeded

Related questions

3 Answers

  • author's profile photo Former Member
    Former Member
    Posted on Oct 12, 2010 at 07:28 AM

    Hi

    Are you getting the issue only in first bucket or all in the buckets of PA.

    If yes, I will suggest to check the date variants in the respective programs.

    Thanks

    Amol

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Oct 12, 2010 at 09:56 AM

    Hi

    Can you check your planning horizion. Go to /SAPAPO/MSDP_ADMIN - Administration of Demand Planning and Supply Network Planning, select the respective planning area  right click and check created time series objects and check the date range.

    You can check if you have date validly in past.

    Thanks

    Amol

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Oct 14, 2010 at 11:29 PM

    Hi Girish,

    Do you get any error logs while uploading the mid-month data.

    The only reason i see this possible is there are non generated CVC in the BI infocube for which the data does not get transferred due to other Characteristic mismatch apart from product.

    Often there are changes in the OLTP system which force some data change in the CVC.

    Are you running a CVC generation program before each load of Planning area?

    Hope you're able to reach answers to your questions based on above.

    Let me know if you need more help

    Thanks

    Ankur Shrivastava

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.