SLOC determination for one material

Hi Gurus

I want SLOC to be determined in outb.delivery for one material only. How can it be configured?

Thanks.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Oct 11, 2010 at 10:10 AM

    Have the item category as TAX or TAW for the other one so that without storage location and of course, with no stock, you can post the goods issue.

    thanks

    G. Lakshmipathi

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Oct 11, 2010 at 08:21 PM

    hi Azat,

    sloc is determined via transaction OVL3. There you have the field 'storage condition' which comes from material masterdata (MARA-RAUBE). Note that the field is editable at plant view, but the data is in MARA table (so general for the material code).

    If you have different storage conditions defined for different materials, then you can configure only for selected ones automatic sloc determination.

    However, can you explain why there is such a need? Because to me this is weird requirement..?

    Regards,

    Dominik Modrzejewski