Inspection Time in planning

Hi,

We are using CTM mfor Production Planning, inspection time is defined for the product in ECC.

The code for product before and after inspection activity is same, and no seperate operation is defined for product.

In ECC we are using standard process in QM for inspection. The issue is I want to capture the inspection time in planning while creating the planned order.

I can use GR processing time for that, but is this the only option or can anyone suggest an alternate method to model inspection time in APO.

Thanks & Regards,

Sanjog Mishrikotkar

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • author's profile photo Former Member
    Former Member
    Posted on Oct 11, 2010 at 12:24 PM

    Hi,

    For basic scheduling of Planned Orders:

    the time taken are 1. GR Proc time, inhouse prodn time and opening period defined in the schedule margin key.

    For lead time scheduling of planned orders

    the time taken are 1. Float after production, times from routing, float before production.

    So i think you can map your inspection time with above timings.

    Thanks,

    nandha

    Thanks,

    nandha

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.