Inspection Time in planning

Former Member
0 Kudos

Hi,

We are using CTM mfor Production Planning, inspection time is defined for the product in ECC.

The code for product before and after inspection activity is same, and no seperate operation is defined for product.

In ECC we are using standard process in QM for inspection. The issue is I want to capture the inspection time in planning while creating the planned order.

I can use GR processing time for that, but is this the only option or can anyone suggest an alternate method to model inspection time in APO.

Thanks & Regards,

Sanjog Mishrikotkar

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

For basic scheduling of Planned Orders:

the time taken are 1. GR Proc time, inhouse prodn time and opening period defined in the schedule margin key.

For lead time scheduling of planned orders

the time taken are 1. Float after production, times from routing, float before production.

So i think you can map your inspection time with above timings.

Thanks,

nandha

Thanks,

nandha