I release the Forcasting schedules based on the creation profile assign to the Scheduling agreement (Lpa)
In the creation profiel i have maintained the Aggegation horizon as 0-60 (days), 60-90(weeks) and 60-999 (months).
after release when i checked the schedules the aggegation is not properly.
how system caculated the the aggegation whether it consider the working day only or calender days
2. what is mean by creation indicator -R ( real time) B - mrp driven
Hi,
It depends upon the Planning Calendar specified in Creation profile customization.
R- Realtime means using ME38
MRP driven is self explanatory and are created by MRP when the source is fixed in sourcelist and MRP indicator maintained.
Hope this helps.