Skip to Content
author's profile photo Former Member
Former Member

scheduling agreement number is not shown in the MD04

Dear all,

The scheduling agreement number is not shown in the MDO4 screen for the material x.

when i check the mrp data for availabiity check as 02 .

if i copy line item of the material in same SA , and enter the forecasting line, system showed in the MD04 for the SA number

Pls help me out to find out the reason.

thanks

vbraj

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • Posted on Oct 11, 2010 at 08:52 AM

    The root cause could be your schedule line category in VOV6 where you should have ticked the box "Req./Assembly".

    thanks

    G. Lakshmipathi

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.