scheduling agreement number is not shown in the MD04

Dear all,

The scheduling agreement number is not shown in the MDO4 screen for the material x.

when i check the mrp data for availabiity check as 02 .

if i copy line item of the material in same SA , and enter the forecasting line, system showed in the MD04 for the SA number

Pls help me out to find out the reason.

thanks

vbraj

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Oct 11, 2010 at 08:52 AM

    The root cause could be your schedule line category in VOV6 where you should have ticked the box "Req./Assembly".

    thanks

    G. Lakshmipathi