Cancel material document(MIGO) thru MBST if stock not consumed.
Change cost centre in ME22N.
Check this link [Cost center change|cost-center-change]
Whether p.o is account assignment with 'K' ?
Hi
If the PO is completely delivered, simply go to KB11N and transfer the value from old cost center to new cost center
If you are yet to receive the goods, reverse the MIGO, change the PO and do MIGO again
Regards
Ajay M
Hello,
Also check KB61, here you have to give your accounting document
You can change cost center here.