We use the COPA module a lot at our company, and we have used the realignment programs to analyze profitablity across different characteristics. Is it possible to run realignment on value fields?

If not, how have other people re-done value fields on COPA to map differently?

Edited by: JDA34 on Oct 11, 2010 5:56 AM

Accepted Solutions (0)

Answers (1)

Answers (1)

ajaycwa1981
Active Contributor
0 Kudos

Hi

You need to use KE21N for this

Re-alignment wont serve the purpose.... Using KE21N in this situation has to be in 2 steps

1. Post -ve value to the same value field for same chars

2. Post +ve value to the reqd value field for same chars

Regards