on 10-11-2010 4:39 AM
Hello all:
what the difference between cost center and responsibility cost center please?
Thx in advance.
Moderator: Please, use F1 functionality and search help.sap.com
Hi ,
I think your question is related to Cost Center Post Field and Responsible Cost Center in WBS Master Data ..
Responsible Cost Center is the cost center where the project activities are carried out .
As per SAP Terminology - Responsible Cost Center is " The key of the cost center of the WBS element where the activity is being carried out.
".
Cost Center Post is the field in Control Data in WBS Element where cost may be booked to cost center in addition to WBS Element . If WBS is real , statistical costs are booked into Cost Center post and vice versa .
Regards
Sarada
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.