Hi Gurus,
My material is as below:
MRP Type: M0
Stategy group:40 Planning with final assembly
Consumption mode :2 Backward and forward consumption
My independent Req is 'VSF Planning with final assembly'
My sales order item category is 'Zwac', rety is using ZWAC-M0-KSV 'Sales order with consumption'
but before i create sales order:
MRP element Received/Requirement quantity
stock
IndReq 100-
After that:
MRP element Received/Requirement quantity
stock
IndReq 100-
Sales order 90-
but i expected like this:
MRP element Received/Requirement quantity
stock
IndReq 10-
Sales order 90-
Do you know what i did wrong , thank you!
Regards,
dragsky