Hello,
In IW31/32> Operation tab> then "Dates" screen.
Is there a way to change Date Restriction choices for "StartPoint" and "End."
Start Point: there are 4 choices: Must Start on, Cannot start before, cannot start after, start from resource planning
End: Must finish on, Cannot finish before, finish not later, finish from confirmation.
We want to limit the choice to 2 optiions on Start and End/ in addtion change the text.
Is this possible.
Thanks,
Hi,
No its not possible to accomplish this in standard using configuration functionality.
You may able to accomplish restricting the values on the drop down through the implicit enhancement functionality available in ECC 6.0.
You will have to make a screen modification to make the associated start point/ end point key text editable.
Regards
Narasimhan
Also bear in mind that these fields are used in other modules, so you don't want to mess around with the data definitions
PeteA