Hi all,
I have a problem with Capacity of Work center (WC).
I have a Internal Activity, and i assigned a WC for this Internal Activity. WC's capacity is 100H/day for 1 number of element.
Work of this WC is 250H, duration 5 days, number of element 1. Default capacity of this WC is distributed by Distribution Key define in Activity. . And they are divided equally between factory days in 5 day. That is capacity requirement is 50H/Day
So, i want to edit this WC's capacity following value:
Day 1: 100H/day
Day 2: 50H/day
day 3: 0H/day
day 4: 0H/day
day 5: 100H/day
How can i do it?? I try to use Dispatch Manually but i cant solve this problem. 😔
Please help me for this case.
Thank all.
NLQ
Dear ,
I have couple of points for you .Do u think that any machine can have Capacity Utlisation more than 100% ?? In your case it is 250% .May be technically you can enter this utilisation for time managemnet , but practically it may not be possible.
As you said WC's capacity is 100H/day for 1 number of element. : I think Work Centre has Operating hours and Avaialble capacity .
Operating hrs depends on your Break Time , Work Centre Start Time , Work Centre End Time , Shift Pattern (Grouping key ) .
Operating hrs =((End Time -Start Time ) -Break Time
If you are working exclusively 8 hrs per day with mentioned Capacity utilisation , then you should have available capacity of 20 hrs (82.501) .So it cant not be 50hrs ( 202.51) -may be three shift total 20 hrs ) .Just check this one .
You should revisit the set up Distibution Key based on Factory Days and carry out same testing in sandbox.
Hope this will address the issue
Regards
JH