Hello
I have some individual materials.
Fot those materials, i have individual needs from SD , and collective needs come from Management Demand.
When I run a MRP, for the individual needs, I have one planned order (qty 1) for one need (Qty 1).
For collective needs come from management demand, I have one planned order per date of need, so i can have a qty <> 1, and i want a fixed order by 1, but i can't.
I tried FX Qty 1, FS , but I always have, one planned order per date of need (if i have 10 need for the same date, i will have one planned order with 10 in qty, and i want 1).
How can i do ?
Thanks
Christian, you mean that for FX = 1 Lot size , the system is using some other setting and creating the planned order by total day requirement ? It is weird... What is the strategy group in the MRP3 view of the material ? Requirement Group in MRP4 ? Individual / Collective in MRP4 ?
Hello
in mrp3 the stategie group is empty.
Mrp4 is individual.
I don't have any problem with collective parts, the batch size is correct.
With individual part number, i have a problem, when the needs come from the management demand.
I have one planned order per date, if i delete manually the planned order, i will have the same problem after running an MRP.
@+
Yes I agree
i have two kinds of needs for an individual part:
- individual needs from Sales orders. with spécific wbs (because I know the configuration)
- collective needs from Demand management without wbs ( because I don't know the configuration, I use MRP3 configurable material with configure variante)
So for the collectif needs, it is impossible to have a planned order with qty 1 (I tried FX=1 and FS 1).
Always the planned order aggregates the qty per date of dependent requirement.
EXEMPLE:
if I need qty 8 for 2010.10.10 I will have a planned order for 10
@+
Add a comment