Hi,
My scenario related to Rework reporting in ECC 6.0.
In my case, When i confirm the Rework at an operation, a Re work order is created automatically through Trigger point.
we account all the expenses against the Rework order and finally we settle the Re work order to the main order.
The rework order does not have the material .
Now how to get the report for the below requirements without involving any ABAP developments.
1. Rework quantity valued at Standard cost ( Rework qty X Standard cost estimate ) at any point of time.
2. How do i capture costs on the Rework order ? is it through regular CO activities ?
3. The rework expenses incurred for the original Order / Material ( Before Rework order settlement to main order).
4. Are there any special reports available for Rework / Scrap ?
Request your help.
Njoy
Siva
Hi,
I have given my inputs.
1. Rework quantity valued at Standard cost ( Rework qty X Standard cost estimate ) at any point of time.
As you have mentioned there is no material involvedin the rework, so the quantity valuation is not possible.
Only acitivity cost related to the rework production order are captured by the child order and settled to the parent order.
2. How do i capture costs on the Rework order ? is it through regular CO activities ?
Generally we wil have a Separate order type for the rework order.
So we need to view the cost collected through this order types in separate order type.
You can ues the coois ORDER confirmation report with the activities confirmed for this order type - but you will not get the cost displayed here.
3. The rework expenses incurred for the original Order / Material ( Before Rework order settlement to main order).
4. Are there any special reports available for Rework / Scrap ?
There are no special reports.
we need to use the standard reports like mb51 with scrap movement type for scrap reports.
coois with rework order type.
as this are not standard practices or best practicies SAP has not delviered any such standard reports.
Reg
Satheesh