Reporting of Rework / Scrap

Hi,

My scenario related to Rework reporting in ECC 6.0.

In my case, When i confirm the Rework at an operation, a Re work order is created automatically through Trigger point.

we account all the expenses against the Rework order and finally we settle the Re work order to the main order.

The rework order does not have the material .

Now how to get the report for the below requirements without involving any ABAP developments.

1. Rework quantity valued at Standard cost ( Rework qty X Standard cost estimate ) at any point of time.

2. How do i capture costs on the Rework order ? is it through regular CO activities ?

3. The rework expenses incurred for the original Order / Material ( Before Rework order settlement to main order).

4. Are there any special reports available for Rework / Scrap ?

Request your help.

Njoy

Siva

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

2 Answers

  • Best Answer
    Posted on Oct 07, 2010 at 03:13 PM

    Hi Siva

    Answers to your questions are as below

    1. Can you plz explain this in more detail.. From what I have understood, you should be able to get reworked qty from PP confirmation reports.. Plz ask your PP guy.... However, this wont give you Qty * Std Cost

    2. Yes, through normal CO activities like operation conf and material issues for rework, if any

    3. This is possible only if you use a secondary cost element for settling the rework order to main order.. May be you can group the relevant primary costs into one secondary cost element instead of one single sec cost ele

    4. There are no separate reports available for them.. Ideal is you create a separate order type.. So, you can use KKBC_HOE or KKO0 reports exclusively on this order type

    Regards

    Ajay M

    Add a comment
    10|10000 characters needed characters exceeded

    • Hi Siva

      My answer applies only when you have settled the order.. Before settlement, I dont think it is possilbe w/o ABAP effort....

      At best, what you can do is to add custom fields to your rework order type which will contain the original material and prod order No... Though this will also involve ABAP effort, but it will give you what you want even without settling the rework order

      Regards

      Ajay M

  • author's profile photo Former Member
    Former Member
    Posted on Oct 07, 2010 at 03:09 PM

    Hi,

    Goto transaction code-KKBC_ORD for analysis cost of rework order and main order.

    Regards,

    Sreekanth

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.