CK40N (one material) reversal

Hi Friends

I performed CK40N for few materials.

Reached until "Marking" and reviewed the costs between future prices and standard prices.

After reviewing decided that for few materials i should not relase the cost.

Hence re-ran the costing after deleting the reqd materials, but erronesouly released cost for one material which should not have been released.

How can i undo the costing run for this one material?

I checked CK44, but it seems it deletes entire costing run?

Kindly assist

Thank you

Sanjay

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

1 Answer

  • author's profile photo Former Member
    Former Member
    Posted on Oct 07, 2010 at 12:20 PM

    HI,

    you can delete released costing results for a single material using CKR1. But take care of the conequences...

    best regards, Christian

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.