Hi,

We have several work centres in one production line. But in costing side we have only one cost centre for one production line.If we use common activity types for all these work centres and if update the common activity rate in cost centre, how we are to differentiate costs among different work centres in same production line.

Please advice.

Regards,

Madhushika

Add a comment
10|10000 characters needed characters exceeded

Related questions

4 Answers

  • author's profile photo Former Member
    Former Member
    Posted on Oct 07, 2010 at 06:35 AM

    Dear Madhushika,

    Welcome to SDN !

    From workcenter activity types will be copied to routing and in routing we give timings to that particular activity types

    Then we need to perfrom costinf CK11N and release the price in CK24

    Same price gets stampped in material master

    Now when you create production order based on order qty you can see target costs gets calculated

    Regards

    Madhu

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Oct 07, 2010 at 06:45 AM

    Dear ,

    What I understood from your requirement is that you have multiple work centre having same Activity Rate-Activity Type , Same Production Cost Centre .In that case you need to analysise Work Centre Wise operation cost or Operation wise cost at that Work Centre level . Basically , this should be differentiated at operation level based on the Standrad Values , total duration ( setup , machine , labout hrs ) , Formula Key invloved .

    From reporting point of view , if you goto -COOIS -Operation -Standrad Profile with Order Type , Plant code and exceute then it will display with Operation Timings as well as if you can goto Select Layout-Change Lay out option -You can choose Price , Costing Variant for same cost centre with different Work Centre and operation combination .

    You can check the same in COHV , CO02-Production Order Header-Costing -Cost Analysis -Itemisiton -Orgin Group

    Hope this will give some idea

    Regards

    JH

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Oct 07, 2010 at 07:03 AM

    HI

    You can decide the cost relevancy in routing of different operation involved thru Costing relevancy indicator in routing > operation details.

    Check and revert

    Regards

    Anupam Sharma

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Oct 08, 2010 at 12:39 PM

    You can display costs in your production order by operation or workcenter, despite the fact that they share the same activiy type, you can control costs by work center.

    COOIS (Order Information System by Operation)

    MCRW (Info System for Resource)

    CO02 ( Production Order, Go to Costs --> Itemization)

    On the other hand, report such as MCRY will give youa total by activity type, regardless of Work Center.

    Hope this helps

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.