Skip to Content
avatar image
Former Member

Basic Start dates should not change, while Changing schedule dates in Production/Process Order

Dear Experts,

When i entered the Basic start date( forward scheduling) in Process order, system automatically gives basic finish date and also scheduled dates. Is there any way that if i change the schedule dates, it should not affect the basic dates of this process order.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • avatar image
    Former Member
    Dec 12, 2016 at 07:18 AM

    HI Bharani,

    In Scheduling type config change auto adjust of dated to do not adjust so that when you change it will not adjust automatically.

    Thanks & Regards,

    Uppalapati Jayadeep

    Add comment
    10|10000 characters needed characters exceeded