Adoption contract service price in Work Order

Former Member
0 Kudos

Hi Experts,

I am creating a external operation by reference to contract service item. i am using service selection dunction to adopt the contract item, it was succesfully unless the price. The price is not adopted. did i miss any configuration setting.

in other way, the price adoption is worked for PR

Pls help.

Thanks. Rgds

Accepted Solutions (0)

Answers (7)

Answers (7)

Former Member
0 Kudos

Hi,

i have maintaned your suggestion, still, the price would not adopted.

Pls help.

Thanks

shrithar_shelvaraj2
Active Participant
0 Kudos

Go for service agreement, in this u need to maintain the service number with price.

so when ever you use the agreement the price will be picked up.

other option maintain the price list for service number also.

this u can have it in vendor, plant and company level etc.

Regards,

Shrithar

Former Member
0 Kudos

Hi Rakesh,

The requirement is to adopt contract service price. i think the info record is for material.

any other idea?

Thanks

Former Member
0 Kudos

Hi Rakesh,

Thanks for the reply, i still cannot get the price adopted.

i hv check the configuration, it was set in Operation price as priotity 1 and Net price order as priority 2.

but still the price does not adopted.

Pls help

Thanks

rakesh_mane
Active Contributor
0 Kudos

Hello..

Please refer the Thread [;

Former Member
0 Kudos

Hi,

we have maintained price correctly in contract.

for PR service (manual-me51n) the price of contract can be adopted well

Thanks. Pls advice

rakesh_mane
Active Contributor
0 Kudos

Hello,

Check SPRO setting for OKP6

1.Net Price from operation

2. Net order price from the purchase order

If price for Operation exists system will pick that price ,if no price in the operation the system automatically picks the price form Purchase Order

In strategy 1 (Net order price from the purchase order), the system only accesses the price in Purchase Order if no Net Price from operation exists for the operation.

If you change the sequence of above stratergy the copying sequence of price will get affected

If above setting is done the system behave as it is

Regards,

Rakesh

Former Member
0 Kudos

Hi Rakesh,

I already did the same thing. is there any configuration setting required for this?

Thanks

Former Member
0 Kudos

check whether you have maintained the price for the services in the contract. Then try in the maintenance order.

rakesh_mane
Active Contributor
0 Kudos

Hello,

Look Thread [;

Regards,

Rakesh