Hi Experts,
I am creating a work order with external operation with reference to agreement/contract item. line of service item is adopted. but the price is not adopted as well. is there any configuration setting that i missed?
Thanks. Pls help
Hi Leni,
You have to click on the service selection button available at the bottom of the External processing screen, this will prompt the list of services entered in the contract. Select the required service click on Adapot Service button.
Ensure that you have mentioned the Contract number in the external services parameters, else the list of services from contract will not be appearing.