Hi Gurus,
In our scenario, we are using bottom-up scheduling method and the Scheduling type as "Forwards". I have given the Project Start date and maintained relationship for all the acitivites along with duration. First time when I scheduled I got the Basic finish dates for Project and the WBS elements. According to this, I presume that whenever there is a change in the duration of any activity and a scheduling is carried out, the finish dates of the all the WBS elements and the Project definition gets changed whereas it is not automatically getting updated. Only if I remove the existing finish dates (which got populated during my first scheduling) and schedule, it is refreshing the dates. Where I am making the mistake ?
Awaiting your expert guidance.
Thanks in advance,
Vinodh