PP/DS planned order from apo to ecc

Dsk
Active Contributor
0 Kudos

Hi,

I am trying to transfert my planned order from APO to ECC

1. I try to publish with c5 it is giving me the below erro

"No change pointers were selected

Message no. /SAPAPO/CIF059

Diagnosis

There are no change pointers that meet your selection criteria. Either no change pointers have been recorded or you selection criteria did not provide any results.

System Response

The system has not selected any change pointers.

Procedure

In the transaction /SAPAPO/C4 check whether the recording of changes is activated for your user. If this is the case, the selection criteria you have entered may not be correct. Change the selection criteria as needed.

"

2. i checked the c4 t.code also i have user as * with all entries as default.

3. i have a IM for the Pld order active

kindly let me know hwo to transfer this order

reg

dsk

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

1.Check in the CCR report whether change pointers exists for prod loc combination.

2.Then check the selection criteria entered in the /SAPAPO/C5 screen.

Thanks,

nandha

Answers (2)

Answers (2)

Dsk
Active Contributor
0 Kudos

closed

aparna_ranganathan
Active Contributor
0 Kudos

Hi dsk

Have you maintained the publication settings in /n/sapapo/cp1 for planned orders ? (inhouse production entry has to be maintained for the plant in question and the target system has to be your R/3 system).

Also check in /n/sapapo/sdp110 if what type of transfer you have specified. Change pointers will be created only if you have maintained periodic transfer option

Thanks

Saradha