Sep 29, 2010 at 12:21 PM

How can I crosscheck Total Planned/Actual Cost in MCI3 (S061) correct?

109 Views

Hi Masters,

I want to crosscheck "Total Planned Cost" and "total Actual Cost" in MCI3(S061) - Location and Planning analysis is correct or not.'

In my current system I am trying to compare the Orders in IW39 and MCI3 but costs are not matching.

I have done some analysis and found that the costs are updated in S061 from PMCO.

But for same Orders in months e.g August I am getting posting for July,August and Semptember.

So I am not sure how I can compare the values of "Total Planned Cost " and Total Actual Cost" in S061 to IW39.

If it is possible to compare what selection criteria I should use for fetcing the Orders from AUFK or IW39. Which dates are I should used ( Date range - Period, Basic start/end dates, Actual start/End Dates).

With Best Regards,

Narendra dere

SAP- Manufacturing.