Rule for Maintenance in standard value key

Former Member
0 Kudos

What is the use of rule for maintenance in standard value key used for creating a work center?

Accepted Solutions (0)

Answers (2)

Answers (2)

former_member196530
Active Contributor
0 Kudos

Dear

Standard values are planned values for the execution of an operation and are maintained in the operation. Typical standard values are, for instance, set-up and processing. The execution time, costs and capacities are calculated in operations using formulas from the work centers and standard values from the operations.

When you assign a work center to an operation, up to six data fields and key words are assigned to the operation via the standard value key of the work center. The standard value key is defined in the Customizing for Work centers by choosing Standard value and is entered in the Basic data screen of the work center.

The rules for maintenance for standard values in the work center Basic data screen determine whether you have to maintain standard values in the operation or whether this is optional.

You can enter default units of measure for the standard values in the work center screen Default values. For inhouse-production operations the default value for the unit of measure of work is maintained in the screen Scheduling

Refer : http://help.sap.com/saphelp_46c/helpdata/es/7e/e62c7dd435d1118b3f0060b03ca329/content.htm

Hope it will clarify your doubt

Regards

JH

sundaresan_velayudam
Active Contributor
0 Kudos

Rule for maintenance

no check, :- If the value is not In routing, system will allow to save the routing

must be entered If the value is not In routing, system will give the error message and not allow to save the routing

should be entered If the value is not In routing system will give the warning message and allow to save the routing

shoulnot be entered : - If the value is maintained In routing ,system will give the warning message and allow to save the routing