Hi PS Gurus,
Do you know of any way for a user to set a custom distribution of costs for a network activity? For example, a cost activity is created for $100,000 which runs for 12 months. In current design, this value will be evenly distributed over the 12 months according to the factory calendar. What the user would like to do is manually adjust the profile by which these costs are planned.
Many thanks, and I hope you all are well.
Cheers, Diana
I can suggest two options:-
1. Create as many distribution profiles as possible and let the user select as per the project need.
2. Create invoice plan for general cost activity as per your distribution requirement.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You can use single unit costing, then you can create amounts of periods you want, and input the value.
Kind regards,
Zhenbo
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.