Scheduling Agreement - Priority for GR Processing Time

former_member184655
Active Contributor
0 Kudos

Dear Forum Members,

While defining Scheduling agreement for a material we can define the GR processing time and Planned Delivery time,likewise we

define in the material master also.

1.While running MRP which one has the higher priority?

2.After running MRP for the schedule line we are able to see only the delivery date,is there any setting to display the release date

or the start date based on the planned delivery time of the scheduling agreement?

Please suggest.

Regards

S Mangalraj

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Mangalraj,

For your question:

1.While running MRP which one has the higher priority?

-->GR processing time MRP-run will take it from material master data

-->Planned delivery time, you can use t-code OMI8 to define the higher priority of SA or material master data

2.After running MRP for the schedule line we are able to see only the delivery date,is there any setting to display the release date or the start date based on the planned delivery time of the scheduling agreement?

-->Yes, in standard SAP system, you only can see the delivery date after MRP-run! As to the release date or the starte date which take planned delivery time of SA into account, it's only used to inform the buyer with purchasing transaction.

Hope my answers can help you!

Good luck

Tao

Former Member
0 Kudos

This message was moderated.

Answers (1)

Answers (1)

former_member184655
Active Contributor
0 Kudos

Dear members,

Can you please give some input for this issue.

Regards

S Mangalraj