I want to report on Initial Review Completion date in service tickets to verify when the ticket was set to in process.Which datasource in C4C has this information?

Regards,

Subhasish

Add comment
10|10000 characters needed characters exceeded

  • Former Member

    Hi Subhasish,

    I have a question,

    # displayed instead of user id in reports. you had similar question earlier. How to solve this issue.

  • Former Member Former Member

    Hi Harish,

    It generally just means that the field is empty.

    Kind regards,
    Gab

  • Former Member Former Member

    Hi Gabriele,

    Thanks for your reply.

    But the report we are trying to generate is for existing user logon activities.

    we have configured territory wise data access/business users, is this causing not to show the user id ?

    and when i generated report for myself "user logon activity", it is still displaying #.

    thanks

  • Get RSS Feed

2 Answers

  • Dec 19, 2016 at 10:21 AM

    Hi,

    You can use Standard Data Source "TICKET TIME POINTS AND CONTACT PARTY" . It has a field called "Request In Process Date" which has initial review completion Date.

    Thanks

    Saurabh

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Dec 19, 2016 at 06:14 PM

    Hi Subhasish,

    You can also add this field to any report built on the standard Tickets datasource (CRMSRQHB).

    Kind regards,
    Gab